User Tools

Site Tools


deltamounting:start

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revisionPrevious revision
Next revision
Previous revision
deltamounting:start [2019/11/05 13:43] ditarantodeltamounting:start [2020/02/27 17:48] (current) ursgraf
Line 1: Line 1:
 ====== Delta mounting instructions ====== ====== Delta mounting instructions ======
 +===== 1. Part list =====
 +{{ :delta:mounting:deltamountinginstructions00.pdf | Part list}}
 +
 ===== 2. Assembly instructions ===== ===== 2. Assembly instructions =====
 Within this document you can find the assembly instructions according to the new low cost delta robot. Within this document you can find the assembly instructions according to the new low cost delta robot.
Line 16: Line 19:
 Place the lower arm into the gauge respectively the lower arm’s spheres into the drillings they belong to (//fig. 2.1//). \\ Place the lower arm into the gauge respectively the lower arm’s spheres into the drillings they belong to (//fig. 2.1//). \\
  
-[{{:deltamounting:deltamountinginstructions01.png|fig. 2.1}}] \\+[{{:delta:mounting:deltamountinginstructions01.png|fig. 2.1}}] \\
 To prevent the glue from pressing away the spheres from the CFK pipe it is recommended to place a magnet on the bottom side of the gauge. The glue takes about 24 hours to reach its ideal dryness. To prevent the glue from pressing away the spheres from the CFK pipe it is recommended to place a magnet on the bottom side of the gauge. The glue takes about 24 hours to reach its ideal dryness.
 Before mounting the next arm unit please clean the gauge carefully from any glue remaining. Before mounting the next arm unit please clean the gauge carefully from any glue remaining.
Line 38: Line 41:
 The next step is to mount the upper arm's motor interface (//fig. 2.2//). The next step is to mount the upper arm's motor interface (//fig. 2.2//).
  
-[{{:deltamounting:deltamountinginstructions02.png|fig. 2.2}}] \\+[{{:delta:mounting:deltamountinginstructions02.png|fig. 2.2}}] \\
 Check first if both halves of the plastic cladding unit can be added so they fit together. If not, it is necessary to fix this issue by using a file to remove plastic print inaccuracies. \\ Check first if both halves of the plastic cladding unit can be added so they fit together. If not, it is necessary to fix this issue by using a file to remove plastic print inaccuracies. \\
 Add the epoxy glue according to its package instructions and fill the cylinder pin holes with it. Then coat a thin film of epoxy glue on the inside surface of the plastic cladding unit. \\ Add the epoxy glue according to its package instructions and fill the cylinder pin holes with it. Then coat a thin film of epoxy glue on the inside surface of the plastic cladding unit. \\
Line 47: Line 50:
 To make sure to keep the motor interface in the right position when the glue dries it is strongly recommended to press (but not to glue yet!) a piece of CFK pipe over the pipe plug. In addition it helps to use a mechanical clamp (do not use too much pressure!) to keep the plastic parts together (//fig. 2.3//). \\ To make sure to keep the motor interface in the right position when the glue dries it is strongly recommended to press (but not to glue yet!) a piece of CFK pipe over the pipe plug. In addition it helps to use a mechanical clamp (do not use too much pressure!) to keep the plastic parts together (//fig. 2.3//). \\
  
-[{{:deltamounting:deltamountinginstructions03.png|fig. 2.3}}] \\+[{{:delta:mounting:deltamountinginstructions03.png|fig. 2.3}}] \\
 Now attach the motor to the motor flange and the motor flange to the gauge. Push the upper arm motor interface onto the motor flange and fix it with allen screws. Now place the two steel spheres into the specified upper arm drill holes. To keep the steel spheres in place, add a cube magnet underneath each of the two steel spheres on the downside of the gauge. Now press each of the remaining two cube magnets into the belonging gaps on the upper arm interface. If necessary they can be mounted by adding some glue. Now glue both of the interfaces and the CFK pipe together (//follow the safety instructions on the glue’s package instructions for working in closed rooms!//). Use the gauge according to //fig. 2.4// to make sure the upper arm’s precision as reliable as possible. Now attach the motor to the motor flange and the motor flange to the gauge. Push the upper arm motor interface onto the motor flange and fix it with allen screws. Now place the two steel spheres into the specified upper arm drill holes. To keep the steel spheres in place, add a cube magnet underneath each of the two steel spheres on the downside of the gauge. Now press each of the remaining two cube magnets into the belonging gaps on the upper arm interface. If necessary they can be mounted by adding some glue. Now glue both of the interfaces and the CFK pipe together (//follow the safety instructions on the glue’s package instructions for working in closed rooms!//). Use the gauge according to //fig. 2.4// to make sure the upper arm’s precision as reliable as possible.
  
-[{{:deltamounting:deltamountinginstructions04.png|fig. 2.4}}] \\+[{{:delta:mounting:deltamountinginstructions04.png|fig. 2.4}}] \\
  
 ==== 2.3 Delta robot ==== ==== 2.3 Delta robot ====
Line 56: Line 59:
  
 Mount the three push buttons and the three motor flanges (M3x10) onto the base plate according to //fig. 2.5//. \\ Mount the three push buttons and the three motor flanges (M3x10) onto the base plate according to //fig. 2.5//. \\
-[{{:deltamounting:deltamountinginstructions05.png|fig. 2.5}}] \\+[{{:delta:mounting:deltamountinginstructions05.png|fig. 2.5}}] \\
 Mount each motor onto a motor flange (M2x5). \\ Mount each motor onto a motor flange (M2x5). \\
 Insert the motor cable carefully into the cable route (//fig. 2.6//). \\ Insert the motor cable carefully into the cable route (//fig. 2.6//). \\
-[{{:deltamounting:deltamountinginstructions06.png|fig. 2.6}}] \\ +[{{:delta:mounting:deltamountinginstructions06.png|fig. 2.6}}] \\ 
-Now put the beagle bone blue board into its beagle bone case and align it by using the according drilling holes on the base plate (//fig. 2.7a//). According to //fig. 2.7b//, make sure to fix the shown corner first (M2.5x25). Then add the case’s top cover and fix the remaining three corners (M2.5x25) according to //fig. 2.8//. \\ +Now put the beagle bone blue board into its beagle bone case and align it by using the according drilling holes on the base plate (//fig. 2.7a//). According to //fig. 2.7b//, make sure to fix the shown corner first (M2.5x25). \\ 
 +[{{:delta:mounting:deltamountinginstructions07.png|fig. 2.7a}}] [{{:delta:mounting:deltamountinginstructions08.png|fig. 2.7b}}] \\ 
 +Then add the case’s top cover and fix the remaining three corners (M2.5x25) according to //fig. 2.8//. \\ 
 +[{{:delta:mounting:deltamountinginstructions09.png|fig. 2.8}}] \\
 Now mount the three upper arms (//fig. 2.9//). \\ Now mount the three upper arms (//fig. 2.9//). \\
 +[{{:delta:mounting:deltamountinginstructions10.png|fig. 2.9}}] \\
 Feel free to mount the base plate according to its design on a surface of your choice (for this specific project there was an IKEA LACK table being used (//fig. 2.10//)). \\ Feel free to mount the base plate according to its design on a surface of your choice (for this specific project there was an IKEA LACK table being used (//fig. 2.10//)). \\
 +[{{:delta:mounting:deltamountinginstructions11.png|fig. 2.10}}] \\
 It is recommended to finish the cabling work //before// mounting the base plate. \\ It is recommended to finish the cabling work //before// mounting the base plate. \\
- 
 The whole cabling between the robot and a PC and its peripheries is meant to be hidden in a cable conduit (//fig. 2.11//). \\ The whole cabling between the robot and a PC and its peripheries is meant to be hidden in a cable conduit (//fig. 2.11//). \\
 +[{{:delta:mounting:deltamountinginstructions12.png|fig. 2.11}}] \\
 Now hang each lower arm into its belonging appliance and mount the tool platform (//fig. 2.12//). \\ Now hang each lower arm into its belonging appliance and mount the tool platform (//fig. 2.12//). \\
 +[{{:delta:mounting:deltamountinginstructions13.png|fig. 2.12}}] \\
 Motors, push buttons and flat-band plugs have to be mounted to the voltage distributor (//fig. 2.13//). \\ Motors, push buttons and flat-band plugs have to be mounted to the voltage distributor (//fig. 2.13//). \\
 +[{{:delta:mounting:deltamountinginstructions14.png|fig. 2.13}}] \\
deltamounting/start.1572957820.txt.gz · Last modified: 2019/11/05 13:43 by ditaranto